CL-01 · Packet contents
PRINT & CHECK OFFThe SIR defines the complete application package in its Appendix F checklist; Con Edison layers its own documentation on top. Structural contents:
- Standardized application — inverter-based (SIR Appendix B) or non-inverter-based (Appendix C) confirm current revision
- Con Edison DG documentation checklist for the project type confirm current revision
- Customer authorization letter
- Single-line diagram; a three-line diagram may be required for PV and battery designs on three-phase systems, showing the wiring configuration at the point of common coupling
- Equipment spec sheets — inverters certified to UL 1741 (supplement SB) with settings per the utility's technical requirements
- Site plan
- Acknowledgement of property owner consent (SIR Appendix H) and site control certification (Appendix J) where applicable
- Standardized interconnection contract (SIR Appendix A) — executed during the process
- Energy storage systems: the ESS application requirements in SIR Appendix K
- Testing paperwork: verification test certification for systems 50 kW or less; Con Edison's solar testing and inspection checklist for larger solar projects
Requirements drift. Get the changes.
When the Con Edison page's change log gets a new entry, we'll email you that entry. Nothing else.
Filing with Con Edison every month?
Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.
SunDocket sample pages are compiled from public sources (2026-08-12). Not legal or engineering advice. Not affiliated with any utility. Verify against the utility's current published requirements before filing.