Con Edison packet checklist

Sample preview — compiled from public sources 2026-08-12

New York · SIR Last reviewed 2026-08-12 Full requirements: Con Edison page

CL-01 · Packet contents

PRINT & CHECK OFF

The SIR defines the complete application package in its Appendix F checklist; Con Edison layers its own documentation on top. Structural contents:

  • Standardized application — inverter-based (SIR Appendix B) or non-inverter-based (Appendix C) confirm current revision
  • Con Edison DG documentation checklist for the project type confirm current revision
  • Customer authorization letter
  • Single-line diagram; a three-line diagram may be required for PV and battery designs on three-phase systems, showing the wiring configuration at the point of common coupling
  • Equipment spec sheets — inverters certified to UL 1741 (supplement SB) with settings per the utility's technical requirements
  • Site plan
  • Acknowledgement of property owner consent (SIR Appendix H) and site control certification (Appendix J) where applicable
  • Standardized interconnection contract (SIR Appendix A) — executed during the process
  • Energy storage systems: the ESS application requirements in SIR Appendix K
  • Testing paperwork: verification test certification for systems 50 kW or less; Con Edison's solar testing and inspection checklist for larger solar projects

Filing with Con Edison every month?

Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.

Become a design partner

SunDocket sample pages are compiled from public sources (2026-08-12). Not legal or engineering advice. Not affiliated with any utility. Verify against the utility's current published requirements before filing.