National Grid packet checklist

Sample preview — compiled from public sources 2026-08-19

New York · NYS SIR Massachusetts · DPU DG tariff Last reviewed 2026-08-19 Full requirements: National Grid page

CL-01 · Packet contents — upstate New York (SIR)

PRINT & CHECK OFF

The structural contents of a National Grid upstate New York interconnection packet under the NYS Standardized Interconnection Requirements. Every form and appendix reference below should be checked against the SIR revision in force before filing.

  • Standardized SIR application — inverter-based or non-inverter-based appendix form confirm current revision — submitted through National Grid's nCAP portal
  • SIR application-package checklist items (Appendix F confirm current revision)
  • Customer authorization tied to the correct National Grid account and service point
  • Single-line diagram; three-line detail where required for three-phase or storage designs
  • Equipment spec sheets — inverters certified to UL 1741 (supplement SB) with settings per National Grid's ESB 756
  • Site plan
  • Property-owner consent and site-control certification where applicable (SIR appendices)
  • Energy storage systems: the ESS application requirements appendix (SIR)
  • Application fee where applicable — none for systems 50 kW or less per the SIR; verify current schedule above 50 kW

CL-02 · Packet contents — Massachusetts (M.D.P.U. No. 1599)

PRINT & CHECK OFF

The structural contents of a National Grid Massachusetts DG interconnection packet under the DPU-approved Standards for Interconnection of Distributed Generation. Check exhibit references against the tariff revision in force.

  • Simplified Process application (tariff Exhibit A — includes the agreement) or Expedited/Standard application (Exhibit C) confirm current revision
  • Pre-application report (Exhibit B) — optional below 250 kW, required at 250 kW and above for Expedited/Standard filings
  • Interconnection Service Agreement for Expedited and Standard projects (Exhibit G)
  • Single-line diagram and equipment spec sheets for listed inverters
  • Landowner consent agreement where applicable (Exhibit I)
  • Schedule Z — additional information required for net metering service
  • Application fee per the tariff fee schedule — $28 Simplified; $4.50/kW (min $300, max $7,500) Expedited/Standard verify current schedule

Filing with National Grid every month?

Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.

Become a design partner

SunDocket sample pages are compiled from public sources (2026-08-19). Not legal or engineering advice. Not affiliated with any utility. Verify against the utility's current published requirements before filing.