TEP packet checklist

Sample preview — compiled from public sources 2026-08-19

Arizona · ACC DGIR Last reviewed 2026-08-19 Full requirements: TEP page

CL-01 · Packet contents

PRINT & CHECK OFF

The structural contents of a TEP packet, from TEP's Interconnection Manual and residential interconnection pages. Which items apply depends on level and configuration.

  • Interconnection application in PowerClerk (tepdg.powerclerk.com), submitted by the installer on the customer's behalf
  • Inverter manufacturer and model details, with equipment technical data — UL 1741 / UL 1741 SA listed, IEEE 1547-2018 conformant
  • Facility site plan
  • One-line electrical drawing
  • Three-line wiring diagram
  • Level 3 (above 2 MW): AC and DC control schematics, a location map, and equipment data sheets
  • Interconnection Agreement executed with TEP (DocuSign for Level 1; AdobeSign for Levels 2–3), including the applicable Exporting System Agreement confirm current form
  • Metering hardware per TEP's material kit — meter socket, hub, disconnect, and labels; a dedicated performance meter is required (TEP-supplied for Level 1 residential grid-tied systems)
  • Service-entrance work compliant with TEP's Electric Service Requirements (SR-702 / SR-703 confirm current revision)
  • After construction: AHJ electrical inspection and clearance, then the Notice of Installation Completion with as-built drawings and photos
  • Go Solar Home Processing Fee per TEP's Statement of Charges verify current schedule

Filing with TEP every month?

Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.

Become a design partner

SunDocket sample pages are compiled from public sources (2026-08-19). Not legal or engineering advice. Not affiliated with any utility. Verify against the utility's current published requirements before filing.