CL-01 · Packet contents — Massachusetts
PRINT & CHECK OFFThe structural contents of an Eversource Massachusetts DG interconnection packet under the DPU-approved Standards for Interconnection of Distributed Generation. Check every form against the tariff revision in force before filing.
- Simplified or Expedited/Standard interconnection application in PowerClerk, tied to the correct customer of record and service point confirm current revision
- Pre-application report — required for systems 250 kW AC and above
- Single-line diagram showing the point of common coupling, disconnects, and protection
- Equipment spec sheets — inverters meeting the IEEE 1547-series requirements Eversource publishes confirm current revision
- Interconnection Service Agreement for Expedited and Standard projects
- Net-metering schedule information where the project takes net metering service
- Application fee per the fee schedule — $0 qualifying Simplified; $100–$300 small network systems; $4.50/kW (min $300, max $7,500) Expedited/Standard verify current schedule
- Filed with the correct DG group — Eastern MA (emdg@eversource.com) or Western MA (wmdg@eversource.com)
CL-02 · Packet contents — Connecticut
PRINT & CHECK OFFThe structural contents of an Eversource Connecticut interconnection packet under the guidelines established per PURA Docket No. 03-01-15RE03, as published on Eversource's Application to Connect page.
- Interconnection application in PowerClerk with e-signature confirm current revision
- One-line electrical schematic
- Site plan showing meter and AC disconnect location
- Proof of insurance — published coverage levels vary by capacity, from $300K to $5M verify current schedule
- Technical specification / data sheets with UL 1741 certification
- Proof of compliance with the applicable IEEE standards
- Guidelines acknowledgment for the correct track — inverter-based 25 kW or less, Fast Track (up to 2 MW), or Study Process (above 2 MW)
- Application fee — $200 (≤25 kW inverter-based) / $500 (Fast Track) / $1,000 + study fees (Study Process) verify current schedule
Requirements drift. Get the changes.
When the Eversource page's change log gets a new entry, we'll email you that entry. Nothing else.
Filing with Eversource every month?
Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.
SunDocket sample pages are compiled from public sources (2026-08-19). Not legal or engineering advice. Not affiliated with any utility. Verify against the utility's current published requirements before filing.