Eversource interconnection requirements

Sample preview — compiled from public sources 2026-08-19

Massachusetts · DPU DG standards Connecticut · PURA guidelines Last reviewed 2026-08-19
SD-01 · Who this applies to REV 2026-08-19

Who this applies to

Eversource runs electric distribution in three New England states. This page covers the two with the most distributed solar activity, each under its own regime, kept separate throughout:

  • Massachusetts (Eastern MA and Western MA service areas) — DG interconnects under the DPU-approved Standards for Interconnection of Distributed Generation, the statewide framework each Massachusetts utility files as its own tariff confirm current tariff revision. Eversource runs separate Eastern MA and Western MA DG groups.
  • Connecticut — generator interconnection follows Eversource's published guidelines established under PURA Docket No. 03-01-15RE03, with tracks split by size and technology.

Covered project types in both states: solar, storage, and solar-plus-storage operating in parallel with the distribution system, residential through commercial scale. New Hampshire is Eversource territory too, but its separate state process is not covered on this page yet — see the FAQ. Wholesale and transmission-level interconnections are out of scope.

SD-02 · Application pathway overview REV 2026-08-19

Application pathway overview

Both states apply through Eversource's PowerClerk online system — application, e-signature, payment, and status tracking in one place. An Eversource.com account is required; Connecticut DG contractor credentials also work for Massachusetts filings.

Massachusetts — three DPU paths

PathTypical projectsReview
Simplified Inverter-based systems 25 kW AC or less on qualifying radial circuits; small systems on networks under 1/15th of customer minimum load Fastest path; the agreement is part of the application
Expedited Listed facilities that pass pre-specified screens on a radial circuit Screen review, with Supplemental Review if a screen fails
Standard Systems above 25 kW AC, non-standard configurations, non-inverter generators, and network projects that don't qualify for Simplified Initial review, then Impact Study and Detailed Study as required. Pre-application report required at 250 kW AC and above.

Connecticut — three PURA-guideline tracks

TrackSizeWhat review looks like
Residential / small inverter-based 25 kW or less Published 15-day review; guidelines document for inverter-based generators 25 kW or less
Fast Track Up to 2 MW Screened review per the Fast Track and Study Process requirements; published 15-day review
Study Process Above 2 MW (or Fast Track failures) Cost-based studies; published 105–120-day review
SD-03 · Required forms & documents STRUCTURE AS OF 2026-08-19

Required forms & documents

Massachusetts: the statewide Standards define the application package; Eversource takes it through PowerClerk. Structural contents:

  • Simplified or Expedited/Standard interconnection application in PowerClerk, tied to the correct customer of record and service point confirm current revision
  • Pre-application report — required for systems 250 kW AC and above
  • Single-line diagram showing the point of common coupling, disconnects, and protection
  • Equipment spec sheets — inverters meeting the IEEE 1547-series requirements Eversource publishes (new inverter requirements effective October 1, 2023 confirm current revision)
  • Interconnection Service Agreement for Expedited and Standard projects
  • Net-metering schedule information where the project takes net metering service
  • Application fee payment per the fee schedule

Connecticut: per Eversource's Application to Connect page and the PURA-docket guidelines:

  • Interconnection application in PowerClerk with e-signature confirm current revision
  • One-line electrical schematic
  • Site plan showing meter and AC disconnect location
  • Proof of insurance — published coverage levels vary by capacity, from $300K to $5M verify current schedule
  • Technical specification / data sheets with UL 1741 certification
  • Proof of compliance with the applicable IEEE standards
  • Guidelines acknowledgment for the correct track — inverter-based 25 kW or less, or Fast Track / Study Process
  • Application fee payment (PowerClerk collects fees; Eversource has published options to pay at the final meter swap for some programs)

Print-ready packet checklist

SD-04 · Fees STRUCTURE AS OF 2026-08-19

Fees

Two separate schedules, both published by Eversource as accessed 2026-08-19.

State · ItemPublished amountNotes
MA · Simplified — 25 kW AC or less, radial circuit $0 verify current schedule Per Eversource's MA application page
MA · Simplified — small network systems $100–$300 verify current schedule Depending on capacity; per Eversource's MA application page
MA · Expedited / Standard $4.50/kW, minimum $300, maximum $7,500 verify current schedule Per Eversource's MA application page; matches the statewide Standards' fee schedule
MA · Impact / Detailed Study, system modifications Actual cost Per the statewide Standards
CT · Inverter-based, 25 kW or less $200 verify current schedule No study fee; per Eversource's CT application page
CT · Fast Track, up to 2 MW $500 verify current schedule No study fee; per Eversource's CT application page
CT · Study Process, above 2 MW $1,000 + cost-based study fees verify current schedule Per Eversource's CT application page

Filing here every month?

Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.

Become a design partner

SD-05 · Typical timeline stages CLOCKS PER PUBLISHED DOCUMENTS

Typical timeline stages

Massachusetts (statewide Standards, business days verify against Eversource's current tariff): every path starts with a 3-day acknowledgment and a 10-day completeness review.

  1. Simplified — total maximum 25 days (30 with a screen #5 failure); the agreement is part of the application.
  2. Expedited — screens within 25 days; Supplemental Review, if needed, 20 days; total maximum 45 days (65 with Supplemental Review).
  3. Standard — initial review 20 days, Impact Study 55 days, Detailed Study 30 days; total maximum 135 days (160 if the application started in Expedited).
  4. Witness test — within 10 business days of the Certificate of Completion, or by mutual agreement.

Connecticut (per Eversource's published table):

  1. Application — submitted, e-signed, and paid in PowerClerk.
  2. Review — 15 days for inverter-based systems 25 kW or less and Fast Track projects up to 2 MW; 105–120 days for Study Process projects above 2 MW.
  3. Studies (Study Process only) — cost-based, scoped per the Fast Track and Study Process requirements.
  4. Build, inspection, and meter work — install to the approved design and complete the utility's witness/meter steps before parallel operation.

Eversource has flagged that equipment lead times on ordered materials are unpredictable — from a couple of months up to a year or longer — which can affect any stage requiring utility-side equipment.

SD-06 · Common deficiency causes COMMONLY CITED · 2026-08-19

Common deficiency causes

Common ways applications fall short of the published requirements above — each item maps to a requirement in Eversource's or the state regulators' cited documents. Not drawn from SunDocket filing data.

  • One-line schematic missing the point of common coupling, disconnect, or protection detail — both states require it explicitly
  • Connecticut site plans that don't show the meter and AC disconnect locations
  • Proof-of-insurance documents missing or below the published coverage level for the project's capacity (Connecticut)
  • Inverter spec sheets without the required UL 1741 certification, or not meeting the IEEE 1547-series requirements Eversource publishes
  • Customer or site data that doesn't match the Eversource account of record
  • Massachusetts filings at 250 kW AC or above submitted without the required pre-application report
  • Wrong track or wrong fee for the project's size and technology — both states' schedules vary by track
  • Filing to the wrong Massachusetts DG group — Eastern MA and Western MA are handled separately
SD-07 · FAQ REV 2026-08-19

FAQ

How long does Eversource interconnection take in Massachusetts?

Massachusetts' DPU-approved Standards for Interconnection of Distributed Generation attach maximum business-day totals to each path — 25 days Simplified (30 with a screen #5 failure), 45 days Expedited (65 with Supplemental Review), and 135 days Standard (160 if the application started in Expedited) — with a 3-day acknowledgment and 10-day completeness review at the front of every path. Verify against the Eversource tariff revision in force when you file.

How long does Eversource interconnection take in Connecticut?

Eversource's Connecticut application page publishes review timelines by track: 15 days for inverter-based systems 25 kW or less, 15 days for Fast Track projects up to 2 MW, and 105 to 120 days for Study Process projects above 2 MW. Verify the current published schedule before filing.

What is the Eversource interconnection application fee?

It depends on the state and track. In Connecticut, Eversource publishes $200 for inverter-based systems 25 kW or less, $500 for Fast Track (up to 2 MW), and $1,000 plus cost-based study fees for the Study Process (above 2 MW) — verify current schedule. In Massachusetts, Eversource publishes $0 for qualifying Simplified applications 25 kW or less on radial circuits, $100 to $300 for small network systems, and $4.50 per kW (minimum $300, maximum $7,500) for Expedited and Standard applications — verify current schedule.

What is PowerClerk?

PowerClerk is the online application system Eversource uses in both Massachusetts and Connecticut to submit, e-sign, pay for, and track interconnection applications through their full lifecycle. An Eversource.com account is needed, and Connecticut DG contractor credentials also work for Massachusetts filings.

What is the Connecticut Fast Track process?

Fast Track is the screened review path in Eversource's Connecticut generator interconnection guidelines, established under PURA Docket No. 03-01-15RE03, for projects up to 2 MW. Projects that do not qualify or that exceed 2 MW go through the Study Process, with cost-based study fees and a longer published review window.

Does this page cover Eversource in New Hampshire?

Not yet. Eversource serves New Hampshire and takes interconnection applications there under a separate state process, but this page does not cover it in depth. Use Eversource's New Hampshire Application to Connect page for that process.

SD-08 · Change log 1 ENTRY

Change log

  • Page created from public sources.
SD-09 · Sources ACCESSED 2026-08-19

Sources