Arizona solar interconnection

Two of Arizona's big three utilities answer to the Corporation Commission. The third answers to its own elected board — and that one fact reorganizes everything about how you file.

Arizona ACC DGIR · SRP Handbook Last reviewed 2026-08-19
AZ-01 · The regulatory split REV 2026-08-19

The regulatory split

The key structural fact about Arizona interconnection: APS and TEP are regulated by the Arizona Corporation Commission; SRP is not.

  • APS and TEP interconnect under the ACC's Distributed Generation Interconnection Rules (A.A.C. R14-2-2601 through R14-2-2628, effective February 25, 2020) — the DGIR. The rules set the application levels and their clocks: Level 1 Super Fast Track (inverter-based, 20 kW or less, certified equipment; notification within 14 calendar days), Level 2 Fast Track (under 2 MW; 21 calendar days), Level 3 Study Track, and supplemental review. Each utility layers its own technical manual, forms, and portal on top.
  • SRP is a political subdivision of the State of Arizona — a public power district whose publicly elected Board sets its prices and fees. The ACC rules do not apply. SRP's requirements come from its own Distributed Generation Interconnection Handbook, which defines its own DER classes (I–IV), screens, review stages, and clearance path.

So an installer working the Phoenix metro area can face both regimes on opposite sides of a street: ACC levels and rule clocks in APS territory, Handbook classes and SRP's published stage estimates in SRP territory. The three utilities do share one surface similarity — all take applications through PowerClerk-based portals — but the forms, screens, and review paths behind the portals differ.

AZ-02 · Utilities covered 3 UTILITIES

Utilities covered

Sample preview

APS

Phoenix & statewide · ACC DGIR

ACC levels and clocks, the PowerClerk packet, three-line diagram and PE-stamp rules, and the PTO path.

Requirements page Packet checklist

Sample preview

TEP

Tucson · ACC DGIR

ACC levels with screens A–J, TEP's Interconnection Manual, installer-filed PowerClerk applications, and the metering material kit.

Requirements page Packet checklist

Sample preview

SRP

Phoenix metro · SRP Handbook (non-ACC)

SRP's own Handbook — DER classes I–IV, its application screens, the AHJ-submitted clearance rule, and commissioning.

Requirements page Packet checklist

AZ-03 · What changes between regimes REV 2026-08-19

What changes between the two regimes

DimensionAPS / TEP (ACC DGIR)SRP (Handbook)
Who sets the rules Arizona Corporation Commission rulemaking; utility manuals implement it SRP's publicly elected Board; the Handbook is the governing document
Project sorting Levels 1–3 by size, certification, and screens (R14-2-2617 through R14-2-2619) DER classes I–IV by AC size, each with its own review path
Review clocks Rule clocks: 14 calendar days (Level 1), 21 calendar days (Level 2); Level 3 by study SRP-published stage estimates in business days (application, design, technical, final review, commissioning)
Clearance handling Permit clearance ("green tag") or accepted letter in lieu, submitted with final documents Clearance must come to SRP from the AHJ itself, or a Certificate In-Lieu of Electrical Clearance signed by customer and contractor
Shared ground PowerClerk-based intake, UL 1741 / IEEE 1547-2018 equipment certification, three-line diagram expectations, Arizona PE stamps where required, and PTO before operation

Filing in Arizona every month?

Design partners get 5 free filings and their territory encoded first — packets produced with dual human review while the software is built.

Become a design partner